Construction in Kaya Grandi will last 4 more weeks
![](https://bes-reporter.com/wp-content/uploads/sites/6/2021/02/image-68.png)
Kralendijk- Construction work is in full swing in Kaya Grandi, it is going well and according to schedule. According to WEB, all work is expected to be completed within the next 4 weeks.
Contractor Bonaire Wegenbouw Maatschappij (BWM) is currently completing phase 1 in Kaya Grandi: digging, laying pipe sections, testing pipe sections, sealing the trench and repairing pavement with clinker bricks from Tourism Corporation Bonaire (TCB) building to Banco di Caribe.
Transition
The transition from phase 1 to phase 2 will be done in the week of March 1st to 5th . Phase 2 is from Banco di Caribe to Littman Jewelers Bonaire. During this transition there will be a short period, namely from Feb 28th to March 5th, when the entire Kaya Grandi will be closed for traffic.
Also read:
- Board reshuffeling in Statia and Saba Chamber
- Vacancy Rijksdienst Caribisch Nederland
- Stinapa Presents ‘Lac pa Semper’ Final Event
- Bonaire Showcases Itself at Duikvaker Dive Expo
- Executive Council and Island Council Meet with UNESCO, KIEN, and NatCom NL