Kralendijk- ContourGlobal Bonaire is expanding the power plant at Karpata in order to cope with the increasing demand of energy on Bonaire.
ContourGlobal will add 5 new machines to the power plant. They will be operational by August 2019. This investment will secure the energy supply on the island for the coming years.
ContourGlobal and WEB Bonaire N.V. are jointly pursuing the possibilities for expansion projects in order to provide a sustainable, reliable and affordable source of electricity for the island and its economy.
CountourGlobal says they realize the project can bring about some inconvenience to the road traffic during the transportation of the machines to Karpata, and thanks residents in advance for their patience and understanding.
More News
-
St. Eustatius
Invasive Cuban Tree Frog Discovered on Statia
-
Education
Extra Boost for Technical Education for Statia, Saba and Bonaire
-
Bonaire
Applications for VOG, Naturalization Test, and Firearm License Simplified
-
Advertisement
Studying in the Netherlands?
-
Sint Maarten
Traffic and General Safety Controls SXM Result in Multiple Arrests
-
Letter to the editor
Concern Regarding Diesel Fume Exposure on the Makana Ferry
-
Aviation & Travel
Flamingo Airport Bonaire working on new Kiss & Ride area
-
Events
Companies in Bonaire Recognized for Investing in BBL Students
More News
-
St. Eustatius
Invasive Cuban Tree Frog Discovered on Statia
-
Education
Extra Boost for Technical Education for Statia, Saba and Bonaire
-
Bonaire
Applications for VOG, Naturalization Test, and Firearm License Simplified
-
Advertisement
Studying in the Netherlands?
-
Sint Maarten
Traffic and General Safety Controls SXM Result in Multiple Arrests
-
Letter to the editor
Concern Regarding Diesel Fume Exposure on the Makana Ferry
-
Aviation & Travel
Flamingo Airport Bonaire working on new Kiss & Ride area
-
Events
Companies in Bonaire Recognized for Investing in BBL Students